Dunlop Park Memorial Pool Upgrade
Under construction

Dunlop Park Memorial Pool Upgrade

Sector

Government

Value

$3,680,000

Completion

November 2026 (forecast) — project currently under construction

Overview

Focus Construct is delivering the Dunlop Park Memorial Pool Upgrade for Brisbane City Council under Council's formal offer/purchase process. Focus is engaged as principal contractor on a fixed lump-sum construction contract (BIF Act progress claims), covering multi-trade building and aquatic upgrade works at an existing public pool facility.

The scope is a full pool facility upgrade: demolition and civil works; concrete structure; structural steel and metalwork; pool shell / aquatic works (with specialist pool builder); filtration, plant and plumbing; waterplay equipment; electrical, mechanical and fire services; architectural fitout (partitions, roofing, joinery, finishes, glazing); external works, fencing and landscaping; design consultants; and provisional items. Works are on a live Council aquatic site requiring coordination of plant, pool drainage/refill interfaces, and specialist long-lead packages.

What made it work
Short 129-day programme
Live pool facility staging
Post-tender value management on plant/waterplay, including alternative solutions due to long lead times
Competitive pool-builder package
Provisional delay/ground allowances
Principal contractor WHS and management plans